When does the 2022 All Access Documentary Edition project have to be completed?

If provided a grant, teams must be able to deliver the Supplementary Program on or before 5:00 pm PT, Dec 9, 2022 and Main Program on or before 5:00 pm PT, Dec 13, 2023.

When planning their projects, applicants should note the following dates:

  • Dec 9, 2022 Supplementary Program Final Delivery
  • Aug 18, 2023 Main Program Rough Cut delivery
  • Oct 13, 2023 Main Program First Fine Cut delivery
  • Oct 27, 2023 Main Program Second Fine Cut delivery
  • Nov 3, 2023 Main Program STORYHIVE Approval Cut
  • Dec 15, 2023 Main Program Final Delivery