When does my STORYHIVE 2020 Podcast Project have to be completed?

If awarded a grant, teams must be able to deliver the finished Podcast Project on or before 5:00 pm PDT, July 27, 2021.

When planning their projects, applicants should note the following dates:

  • May 25, 2021 Rough Cut delivery  (3 x 15+ min episodes)
  • June 15, 2021 First Fine Cut delivery (3 x 15+ min episodes)
  • June 29, 2021 Second Fine Cut delivery (3 x 15+ min episodes)
  • July 6, 2021  STORYHIVE Approval Cut delivery (3 x 15+ min episodes)
  • July 27, 2021 Final Delivery of Project to TELUS STORYHIVE
  • August  2021 Official Edition Launch on TELUS Optik TV and STORYHIVE YouTube channel (date to be confirmed)