When does the 2020 Local Heroes documentary project have to be completed?

If awarded a grant, teams must be able to deliver the finished documentary program and supplementary behind the scenes program on or before 5:00 pm PDT, July 14, 2021.

When planning their projects, applicants should note the following dates:

May 4, 2021       Rough cut delivery
June 1, 2021       First version fine cut delivery
June 15, 2021     Second version fine cut delivery
June 23, 2021     STORYHIVE approval cut
July 14, 2021      Final delivery of completed program